System reboot: Alberta proposes a new regulatory framework for data centres

On November 18, 2026, the Government of Alberta introduced Bill 42, the Energy, Environment and Utilities Statutes Amendment Act, 2026 (Bill). Among other things, the Bill proposes amendments to the Electric Utilities Act (EUA), the Hydro and Electric Energy Act (HEEA) and the Alberta Utilities Commission Act (AUC Act) that would significantly change how data centres in Alberta are configured, connected to the grid, and approved. The amendments come into force on proclamation.
The Bill primarily does two things with respect to data centres.
- Creates a new regulatory category for "designated data centre systems" (DDCS). The DDCS framework allows large data centres that bring their own generation to self-supply and export, and requires the owners of a DDCS, rather than Alberta ratepayers, to bear the costs of its internal transmission facilities.
- Makes the Alberta Utilities Commission (Commission) the primary regulator of the construction and operation of data centres above a prescribed size, a role that municipalities have largely held to date as part of municipal land planning authority.
The Bill builds on the Data Centre Regulation, enacted in June 2026, which codified Alberta's "bring your own generation" (BYOG) approach to connecting large data centres to the Alberta Interconnected Electric System (AIES). That regulation did not address the barriers to co-locating a data centre with its own generation or the approval of the data centre itself. The Bill addresses both.
This post provides an overview of the DDCS framework and the broader regulation of data centres under the Bill, and highlights the issues that remain to be addressed in regulations and Commission rules.
Key takeaways
- A data centre system with on-site generation and a maximum demand from the transmission system of at least 75 MW (or a lower threshold set by the Alberta Electric System Operator (AESO)) may apply to the Commission for designation as a DDCS, which permits self-supply and export.
- The costs of transmission facilities within a DDCS are excluded from AESO tariffs. Those facilities may be developed by proponents, third parties or incumbent transmission facility owners (TFOs), who may recover their costs from the DDCS owners under contract. Where a TFO provides transmission facilities and services within a DDCS, it may recover the associated costs under a DDCS tariff that prescribes rates to be charged directly to the DDCS responsible person.
- No person may construct or operate a data centre above a prescribed size, which the Government has indicated will be 10 MW, without Commission approval. Commission approvals of data centres and DDCS orders will prevail over municipal land use planning and development decisions.
- Most of the announced siting rules, including a 600-metre setback from homes and farmland restrictions, will be set out in forthcoming regulations.
Designated data centre systems
The Bill defines a "data centre system" as an electric energy system that operates primarily for the use of a data centre. A data centre system may include the data centre, the generating units and energy storage facilities that supply it, and the distribution system and transmission lines that connect those components. A data centre system becomes a DDCS only by order of the Commission (or by designation in the Bill itself, as the government has proposed to do for the Meta Sturgeon County Data Centre).
How does a data centre system qualify for DDCS designation?
A person may apply to the Commission to designate a data centre system, or part of one, only with the written consent of each owner of the system. In addition to anything required by Commission rules (which have not yet been published), the application must include each owner's written consent, the AESO's assessment of the system's impact on the reliability and adequacy of the AIES, and evidence that all costs of each transmission facility forming part of the system will be wholly paid by its owners.
The reliability assessment requirement is notable. A proponent must obtain the AESO's assessment before applying, but the EUA does not establish a process for assessing a particular data centre system. We believe that the process, timing, and criteria will likely be addressed in regulations or ISO rules.
Before designating a data centre system, the Commission must consider whether the designation could reasonably be expected to ensure that the system's owners wholly pay for its transmission facilities, support the efficient exchange of electric energy with the AIES, and, based on the AESO's assessment, maintain or improve the reliability and adequacy of the AIES. The Commission may designate the system only if it is satisfied of these outcomes and that the system:
- has at least one generating unit located on the property where the system is located that is intended to serve the system; and
- has a maximum demand directly from the transmission system of at least 75 MW, or a lower threshold established by the AESO.
These criteria limit designation to large data centres that bring their own generation, consistent with the AESO's prioritization of BYOG projects. The Commission may attach any term or condition it considers necessary to a designation and may make rules respecting applications and designations. As such, much of the practical process, and the ongoing obligations of a DDCS, will be found in Commission rules that have not yet been published.
Self-supply and export
As a starting point, the EUA provides that all electric energy produced in Alberta and connected to the AIES must be offered into the power pool. The existing exemptions from this rule (the self-supply and export exemption and the industrial system designation) are not well suited to data centres co-located with generation.
The Bill addresses this gap by amending section 2(1) of the EUA to exempt the electricity that a DDCS produces and directly consumes from the application of the EUA. Similar to a designated industrial system, a DDCS will not be required to offer all of its generation into the power pool and may self-supply and export.
Transmission infrastructure within a DDCS
The Bill creates a distinct framework for transmission infrastructure that forms part of a DDCS. The definition of "interconnected electric system" in the EUA is amended to exclude distribution and transmission facilities that form part of a DDCS, so the internal wires of a DDCS will sit outside the AIES and the regulated transmission and distribution framework.
The Bill also streamlines approvals. Unless the Commission directs otherwise, a transmission line forming part of a DDCS, on the DDCS lands or across a public highway dividing them, will not require a separate permit or licence under the HEEA. The exemption turns on the line's function and location, not on whether its owner is an incumbent TFO.
Together, these provisions support the development of internal DDCS transmission infrastructure by data centre proponents, third-party infrastructure providers, and incumbent TFOs. The opportunity is specific to infrastructure forming part of a DDCS, not a general right to develop transmission facilities serving the AIES.
Those facilities are not entirely private. Under a new section 40.1 of the EUA, which closely follows the existing regime for industrial systems, the AESO may apply to the Commission for access to a DDCS's transmission facilities where they are required for system access service. The Commission may order access if it is satisfied that access is required and that the needs of the DDCS, including its capability and reliability, will continue to be met, and may set the rates that the DDCS owner may charge the AESO.
Tariffs and cost recovery
The Bill makes a series of coordinated amendments to the EUA so that the costs of transmission infrastructure within a DDCS are borne by its owners, consistent with the Government's stated objective that data centre proponents pay for their own power infrastructure. The AESO's rates must not include the costs of a transmission facility forming part of a DDCS. Part 9 of the EUA, which governs utility tariffs, will generally not apply to a DDCS, and the Commission must ensure that the regulated rate paid by ratepayers does not include the costs of DDCS transmission or distribution facilities.
The changes to TFO tariffs are particularly significant. A TFO will not be required to file a tariff for a transmission facility forming part of a DDCS. Instead, if a TFO provides transmission facilities and services within a DDCS, it may recover the associated costs under a DDCS tariff that prescribes rates to be charged directly to the DDCS responsible person.
The TFO would file this tariff, together with a legally binding contract with a DDCS owner, showing how the facility's costs will be recovered and that none are included in its general tariff. This allows an incumbent TFO to develop internal DDCS infrastructure and recover its costs directly from the DDCS owner, while preserving the requirement that DDCS owners, rather than other ratepayers, bear those costs.
However, when the AESO applies for approval of its tariff, the Commission must have regard to the principle that the tariff give the AESO a reasonable opportunity to recover a just and reasonable share of the costs associated with a connection to the AIES from the responsible person for a DDCS connected to the AIES, and from any data centre connected to the AIES.
The responsible person
Each DDCS has a "responsible person": the applicant for a Commission designation, or a prescribed person for a DDCS designated in the Bill. The responsible person is the primary point of accountability for the DDCS. This matters because a data centre system will often include assets owned by different parties, such as a data centre owner, a generator, and a TFO. Each owner must consent to the application, but once the system is designated, the responsible person controls its relationship with the AESO and its participation in the electricity market.
However, to the extent a regulated TFO or distribution facility owner (“DFO”) supplies facilities to a DDCS, the facilities will still be regulated by the AUC and the duties of the TFO and DFO to co-operate with the AESO remain.
Regulation of data centres generally
In addition to the DDCS framework, the Bill brings data centres (not just DDCS) within the scope of the HEEA.
Which data centres require Commission approval?
Under a proposed section 11.1 of the HEEA, no person may construct or operate a data centre with a maximum demand of a prescribed amount unless the construction or operation is approved by an order of the Commission and complies with the regulations. The Government has indicated that the threshold will be 10 MW.
Applications will be subject to the Commission's public interest test under the AUC Act, which considers a project's social, economic and environmental effects. The Bill also extends many of the Commission's existing powers over power plants to data centres, including powers to inspect facilities and records and to require changes to plans, specifications, and location.
Data centres already under construction or in operation will be deemed to hold the required Commission approval. However, it is currently not clear which stage of construction will satisfy this requirement. We expect there will be further guidance indicating the specific stage of development that qualifies for the deemed approval.
Project siting: Where can data centres be built?
The key parameters that will determine where data centres can be built are not in the Bill, and will be set out in regulations the Government intends to develop with municipalities, industry, Indigenous communities and Albertans.
The Bill itself contains one interim siting measure. Where a data centre is proposed on designated high-quality agricultural land, its construction or operation must also be approved by an order of the Lieutenant Governor in Council. Both the definition and the designation of high-quality agricultural land are left to regulations. This Cabinet approval requirement ceases to have effect on September 20, 2027, which suggests that the longer-term restrictions on farmland will be implemented through the regulations.
The Bill also authorizes regulations specifying minimum setbacks from property boundaries, land of a particular type or use, and structures, and establishing a right of a municipality to request an exemption from or variance to a setback. The Government has indicated that the regulations will establish a minimum setback of 600 metres from the nearest home for data centres of 10 MW or more.
Municipalities may request an alternative setback from the Commission where local planning supports compatible development, and Designated Industrial Zones, brownfield sites and existing power generation sites will be recognized to encourage development in those areas.
Municipal land use planning
To date, municipalities have regulated the data centre facility itself through land use planning and development permits, while the Commission's role has been limited to approving the associated power plant, energy storage, and transmission facilities. The Bill would not eliminate municipal land use authority, but by establishing the Commission as the primary regulator of data centres, it could significantly limit municipal discretion over data centre development.
Under section 619 of the Municipal Government Act, an approval or other authorization granted by the Commission prevails over any municipal statutory plan, land use bylaw, subdivision decision or development decision. Where a subsequent application to the municipality, such as a development permit application, is consistent with the Commission's approval, the municipality must approve it to the extent that it complies with that approval. In our view, this priority will extend to a Commission approval of a data centre and to a DDCS designation order. This is consistent with the Government's statement that the Commission would become the "primary provincial regulator" of data centres of 10 MW or more, ensuring that rules for setbacks, noise, lighting, heat recovery, water use and farmland protection are "consistently applied."
Municipal planning will remain relevant. As with power plants, we expect the Commission to consider a data centre's consistency with municipal plans, and the host municipality's views, in assessing the public interest. However, the level of deference it will give municipalities is not yet clear. The only formal municipal role contemplated by the Bill relates to setbacks: municipal planning, such as designating lands for industrial or data centre development, may support a request for a reduced setback, but the final decision will rest with the Commission.
Looking ahead
Bill 42 represents a significant shift in how data centres are regulated in Alberta.
For large data centres that bring their own generation, the DDCS framework enables self-supply and export, and places the full cost of internal transmission facilities on the owners. It also creates a framework for new transmission infrastructure serving data centres outside the AIES, which may be developed and operated by third parties, including established TFOs that recover their costs from DDCS owners by bilateral agreement or a DDCS-specific tariff.
For data centres generally, the Commission will be the primary regulator of construction and operation.
However, many of the details that will determine project viability remain outstanding, including:
- Siting requirements: minimum setbacks, the availability of setback variances and the lands subject to agricultural restrictions; and
- DDCS designation: the process, criteria, and timing for obtaining the AESO reliability assessment that must accompany an application for DDCS designation.
The Bill is at an early stage in the legislative process and may be amended as it proceeds through the Legislature.
Lastly, the AESO is yet to publish the BYOG connection process and launch its first intake. Once launched, large data centres can submit requests for access to the AIES, which commences the AESO's connection process.
Our team at McCarthy Tétrault will continue to monitor developments related to Bill 42 and the regulation of data centres in Alberta, along with other legislative and regulatory developments such as the BYOG connection process and provide updates.